With the favorable outcome of the hearing held in September, the staff
of Wyndholme is moving ahead at FULL SPEED!
Why? So that construction can commence on January,
2001!
These are just some of the steps...
- Obtain final building permits.
- Obtain testing and inspection proposals for concrete and steel
inspection.
- Obtain survey stakeout proposal for building controls.
- Finalize design services with WV’s architect, Design Collective.
- Finalize construction schedule with early move-in dates.
- Schedule heavy equipment.
- Set up all construction administration procedures for contracts,
etc.
- Interview and hire a superintendent by December 15, 2000.
- Design and complete “design center” to allow future residents
to finalize their choices of finishes in their units by February
2001.
Thanks to the We’re on the Move!

Project Construction Schedule
The following outlines the construction events planned to complete
and allow early move-in to The Watson House by October, 2001.
| - Break Ground |
January 15, 2001 |
| - Foundation Complete |
February 23, 2001 |
| - First Floor Concrete Complete |
March 15, 2001 |
| - Second Floor Concrete Complete |
April 4, 2001 |
| - Third Floor Concrete Complete |
April 18, 2001 |
| - Fourth Floor Concrete Complete |
May 4, 2001 |
| - Fifth Floor Concrete Complete |
May 21, 2001 |
| - Sixth Floor Concrete Complete |
June 5, 2001 |
| - Roof Trussing / Sheathing Complete |
July 3, 2001 |
| - Early Occupancy Move-In |
October 5, 2001 |
Allowance of (2) Weeks For Weather.
Preliminary Marketing & Construction Schedule Contingent on
Financing.
|